Elm Street Improvements


2024 public improvement project
Project description


The proposed Project includes approximately 600 feet of improvements on Elm Street from Colfax Avenue to Harrison Street.
 
 The following major improvements are included in this project:

  • ​Installation of 600 feet of new 8-inch Polyvinyl Chloride (PVC) water main with new 1 ½-inch water service lines and b-boxes
  • Replacement of 208 feet of existing storm sewer with new 12-inch and 18-inch storm sewer
  • New curb and gutter and 5-foot wide sidewalk. In-kind driveway apron repairs as needed
  • Road reconstruction with asphalt pavement
  • Parkway restorations with sod

LincolnMap2023.png

Contact information

Project Manager: Dayvohn Braxton
(847) 904-4238
dbraxton@glenview.il.us

Egineering ​Inspector: William Krueger
(847) 361-1049
wkrueger@glenview.il.us​

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: DiMeo Brothers Inc. of Elk Grove Village, Illinois

Budget: $878,000​

​​​Tentative Schedule

  • ​​​Design open house – October 16, 2023
  • Bid award – January 9, 2024
  • Resident pre-construction meeting – February 13, 2024, 6 p.m. at Village Hall
  • Approximate starting date of construction – March 2024
  • Approximate completion of construction – May 2024
Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.


​​​Notices

Pre-construction meeting letter​

Open House letter

​​​Handouts​

Design meeting presentation

Pre-construction meeting presentation

​​​Board of Trustees actions

Resolution & Staff Report

​​​Project Updates

Sign up​ to be emailed project updates.​​