The Village of Glenview

Wagner Road Improvements


2024 public improvement project
Project description


The proposed Project includes approximately 0.45 miles of improvements on Wagner Road from East Lake Avenue to Kenilworth Lane.
 
 The following major improvements are included in this project:

  • ​Installation of 2,500 feet of new 8-inch Polyvinyl Chloride (PVC) water main with new 1 ½-inch water service lines and b-boxes
  • Sidewalk removal and replacement
  • Pavement patching
  • Parkway and driveway restoration of areas affected during construction

LincolnMap2023.png

Contact information

Project Manager: Eric Pugh
(847) 904-4235

epugh@glenview.il.us​

Engineering Inspector: Jeff Yonke
(847) 904-9715
jyonke@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: PirTano Construction of Elmhurst, Illinois

Budget: $1.5 million

​​​Tentative Schedule

  • Bid award date – March 2024 
  • Resident pre-construction meeting – TBD
  • Approximate starting date of construction – April 2024
  • Approximate completion of construction – June 2024
Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.


​​​Notices

Pre-construction meeting letter​

​​​Handouts

Design meeting handout

​​​Board of Trustees actions

Resolution & Staff Report​

​​​Project Updates

Sign up​ to be emailed project updates.​​